19.12.2023: The installation of the surface layer of our vehicle dynamics area has been completed to such an extent that it is now largely ready for use. The same applies to the new cross approach. We will of course keep you updated here as soon as the work is completed.
The aim of this year's work is to enable you to carry out Euro NCAP tests in accordance with the latest protocols and, in addition to the construction of a new cross approach, we are also renewing the surface of the dynamic driving area.
We will make every effort to minimise the impact of the works on regular testing and any resulting temporary closures of sections of track, and we will keep you informed of current and forthcoming works on this website. You will always find the latest information here.
Do you have any questions? Our team is ready to advise you:
Phone +49 2464 979 83 10
Email
Legend
New construction area
Refurbishment area
New construction of the crossing
For the validation and testing of new assistance systems, tests at high speeds are increasingly required. We are happy to comply with this request and are setting up a new intersection with a transverse approach from the oval on the vehicle dynamics area.
Refurbishment of Vehicle Dynamics Area's surface
The Vehicle dynamics area was built in 2009 and now needs to be renewed due to aging.
Schedule
Period | Construction task | |
---|---|---|
21 August 2023 | Start of construction work, initially for the cross approach to the new intersection on the vehicle dynamics area | |
15 September 2023 | Paving of the asphalt base layer on the cross approach | |
19 September 2023 | Paving the surface course on the cross approach | |
calender week 42 | Removal of the old surface layer of the vehicle dynamics area | |
calender week 43 | Preparation of the asphalt binder surface of the vehicle dynamics area | |
calender week 52 | Installation of the new asphalt surface layer of the vehicle dynamics area | |
Planned completion of the construction tasks |
Video and image gallery
Here, interested parties can get a few impressions of the construction measures.
Start of milling work on the vehicle dynamics area